Pre-Feature Activation Overview

The pre-activation procedures shown in the following table may be executed outside a maintenance window if desired. Procedure completion times shown here are estimates. Times may vary due to differences in database size, network configuration and loading, user experience, and user preparation.

Table 2-1 Pre-Feature Activation Overview

Procedure Elapsed Time (Hours:Minutes) Feature Activation Preparation Procedures
  This Step Cum.  
System Topology Check (0) 0:00-1:00 0:00-1:00
  • Verify Network Element Configuration data.
  • Verify Server Group Configuration data.
  • Analyze and plan DA-MP restart sequence.
Perform Health Check (0) 0:01-0:20 1:01-1:20
  • Verify server status.
  • Log all current alarms.