Mapped Projects Tab (System Activity Sheet)
The Mapped Projects tab lists the P6 projects drawn from the Integration tab of shell details into the Activity Sheet.
The Mapped Projects tab toolbar options are:
The toolbar options are:
- Assign Rate Sheet
See Assign Rate Sheet for details.
- Recost
See Recost for details.
- Refresh
- Find on Page
Use the toolbar options to assign a shell-level rate sheet to selected projects, recost resource loaded or cost loaded projects, refresh page, and find an item displayed on the page respectively.
The Mapped Projects tab columns are:
- Project ID
- Project Name
- Project Type: The values are Current or Baseline
- Project Start Date
- Data Date: The date a project is updated in P6
- Schedule Type: The values are Duration, Resource, or Cost
- ETC Technique: The formula used to calculate the Estimate to Complete. For example: PF = 1/CPI; PF = 1; (1/CPI)*(BAC - EV); 0.75 * (BAC - EV)
Note: When entering the percentage values in your sheet, if you are working in Classic View, then enter the value by using decimal number format. For example, for ten percent, enter: 0.1, and if you are working in Standard View, then enter the value by using percent format. For example, for ten percent, enter: 10%. The value that Unifier uses to validate the value of the Percentage column, when applicable, will be: 0-100.
- Rate Sheet (Planning): The Master Rate Sheet or a shell-level rate sheet used to calculate the costs.
- Rate Sheet (Actuals): The Master Rate Sheet or a shell-level rate sheet used to calculate the costs.