Activity Sheets Log and Manual Activity Sheets
Activity Sheets Log
The Activity Sheets log contains a list of manually created activity sheets. The log also contains the System Activity Sheet. The activity sheets listed are referred to as manual activity sheets.
All the activity sheets that are defined in Unifier will be displayed with source type as 'Custom' in the Activity Sheets log.
Manual Activity Sheet
To create and maintain project schedules within the system, you can manually define activity sheets.
A manual activity sheet captures the:
- Schedule of activities, within a project
- Resource assignments
- Rate
Note: When you assign resources or roles that have multiple rates to an activity sheet, in order to update the total cost (Total Cost value), you must reschedule, or recost, the activity sheet; otherwise, the system will assign earliest assigned resources or roles rates (price/unit) to the activity sheet, and you will not be able to view the correct accumulated cost.
A manual activity sheet also tracks the progress of activities, over the life time of the project.
Note: For information about the System Activity Sheet, refer to the Activity Manager section in the Unifier Earned Value Management User Guide.
You can use an activity sheet to:
- Define simple project schedules.
- Define tasks, milestones, and relationships between tasks, to enhance user experience.
- Assign resources and track project progress by capturing actuals and calculating remaining work that needs to be done.
In an activity sheet you can:
- Set the view to WBS and add activities or update and remove the activities in the WBS view, similar to the Default view.
- Include attachments and comments for the activities.
- View the History Log (within Activity Sheet and Schedule) by using the Data Date.
- Add, edit, and remove the activities and dependencies and assignments in the user defined views. Also will be able to view the dates, costs, units, and other summary data within the WBS hierarchy view.
- Within the WBS hierarchy, add, copy, or remove the activities in WBS view and user-defined views.
- Add, edit, or remove both the column and row data in user-defined views.
- Add additional notes to the tasks or activities.
- Schedule the activities based on data date and view the schedule history.
In the Activity Sheet the following two default views are available:
- Default View
- WBS View
Note: Any existing views that were created prior to the 20.10 upgrade will not be seen in the View drop-down field.
The Default View will be seen by default when you open the sheet. In the Default View drop-down field, all of the activities will be in flat mode.
When you select the WBS View drop-down field, all of the activities within the sheet will be grouped by WBS hierarchy. At WBS (Summary level), all of the costs show the sum of the costs of all of the activities, as well as the costs that are received at the summary level.
The Start and Finish dates, in the WBS row, will show the earliest start date and latest finish dates for all of the activities under that WBS.
All the attributes defined in the Activity Attribute form will be displayed as columns in the WBS View, similar to the Default View. The order of columns will be the same as selected in the design.
You can create views with filters, groupings, and so forth (within an activity sheet) in order to view the filtered and small list of activities and associated columns, instead of scrolling down and right to navigate to specific activities.
For the default and user-defined views, you can perform the following functions, in addition to adding, deleting, and updating the activities and the schedules:
- Drag and drop columns and reorder the columns, except the first 2 columns (Activity ID and Activity Name) which are fixed.
- Click at a column header to change the Sort By option.
- Right-click at a column header and select Lock after this column option to lock a column.
- Right-click at a column and select Lock after this column option to lock a column.
Note: You cannot lock before this column beyond the Activity Name column.
Similar to a Cost Sheet or a WBS Sheet, you can group selected columns in the sheet.
Related Topics
Last Published Sunday, July 20, 2025