Adding Portfolio Budget Curve for Cash Flow by Business Process (Commitments)
To add Portfolio Budget (Approved Budget) curve for cash flow by Business Process (Commitments):
- Select the cash flow from the Cash Flow log.
- Click the gear menu ( ) and click the Properties option to open the Cash Flow Properties window (or the Cash Flow Properties worksheet).
- In the General pane select Business Process (Commitments).
- In the Curves pane select Approved Budget.
- The Approved Budget window (Curve Type: Portfolio Budget) opens.
- Proceed to set up the following parameters:
Cost | Select an option (from the Distribute amount) from field list. The choices are:
|
---|---|
Currency | Click to open the Select Currency window and select the currency for the Portfolio Budget type curve. See Portfolio Budget Curve and Currency for more information. |
Variance | Select Inflow or Outflow or leave the field empty. |
To add Portfolio Budget (Original Budget) curve for cash flow by Business Process (Commitments):
- Select the cash flow from the Cash Flow log.
- Click the gear menu ( ) and click the Properties option to open the Cash Flow Properties window (or the Cash Flow Properties worksheet).
- In the General pane select Business Process (Commitments).
- In the Curves pane select Original Budget.
- The Original Budget window (Curve Type: Portfolio Budget) opens.
- Proceed to set up the following parameters:
Cost | Select an option (from the Distribute amount) from field list. The choices are:
|
---|---|
Currency | Click to open the Select Currency window and select the currency for the Portfolio Budget type curve. See Portfolio Budget Curve and Currency for more information. |
Variance | Select Inflow or Outflow or leave the field empty. |
To add Portfolio Budget (Shared Budget) curve for cash flow by Business Process (Commitments):
- Select the cash flow from the Cash Flow log.
- Click the gear menu ( ) and click the Properties option to open the Cash Flow Properties window (or the Cash Flow Properties worksheet).
- In the General pane select Business Process (Commitments).
- In the Curves pane select Shared Budget.
- The Shared Budget window (Curve Type: Portfolio Budget) opens.
- Proceed to set up the following parameters:
Cost | Select an option (from the Distribute amount) from field list. The choices are:
|
---|---|
Currency | Click to open the Select Currency window and select the currency for the Portfolio Budget type curve. See Portfolio Budget Curve and Currency for more information. |
Variance | Select Inflow or Outflow or leave the field empty. |