Creating a Commitment Funding Sheet

The Commitment Funding Sheet allows you to allocate project or shell funds to a specific "commitment" (base commit) business process record (for example, a contract or a purchase order). Changes to the original contract through the use of associated change commits will also be reflected on the funding sheet. The commitment funding sheet is also used to track the consumption of those funds as spends business processes (invoices or payment applications) are created.

There is one commitment funding sheet for each base commit business process record. You create the sheet directly from the base commit record once it reaches a step at which funding has been enabled. (For workflow BPs, funding can be enabled per step; for non-workflow BPs, funding will be enabled when the form is editable. The funding sheet may also be available for viewing on view forms, depending on the design. The funding sheet is available if a Funding button is present on the base or change commit record toolbar.)

Be sure the following is in place before creating the commitment funding sheet:

If the fund assignment levels and rules have been defined in the structure, then these will be copied to the new sheet. These definitions can be added or edited in the sheet as needed.

The user who creates the sheet becomes the owner and automatically has full permissions to view and edit the sheet. If other users will need to view or edit the sheet, you will need to give them permission.

After the sheet is created, you then allocate funding for that record from the available project or shell funds. Fund allocation is done manually on the commitment funding sheet; allocation and consumption can be tracked on the project/shell funding sheet by adding the appropriate columns.

To create a commitment funding sheet

  1. Go to your project or shell (User mode).
  2. Click the Cost Manager node to expand it.
  3. Click the Commitment Funding Sheet sub-node to open the Commitment Funding Sheet log.
  4. Hover over the base commit business process record on which you want to perform commitment funding.
  5. If commitment funding has been enabled on the base commit business process record, and on the base commit business process record is in current step, then when you open the base commit business process record (gear menu > Open Base Record) and click the Menu Options drop-down, the Funding option will be included in the list of options.

    Note: If the Funding option is not available, then contact your administrator to verify that commitment funding is available for the business process, that it is available on the current step, and that you have the proper permissions. In addition, it is possible that on some steps (and on View Forms), the Funding option will be present, but the option has been designed to open a view-only version of the sheet.

  6. Click Funding to open the Commitment Funding Sheet (<Base Record Name BP>) window.
  7. Click Fund Assignment to open the window and complete the commitment funding.