Opening Generic Cost Sheet
To open a generic cost sheet
- Go to the project/shell tab and switch to User mode.
- In the left Navigator, click Configurable Manager > Generic Cost Manager.
The Generic Cost Manager log lists all the generic cost sheets.
- Select a generic cost sheet and click the gear menu ( ) to open it.
- Click Open to open the generic cost sheet (Generic Cost Manager overlay window) log.
You work with a generic cost sheet in the same way as a standard cost sheet, seen in projects and CBS shells. The difference is that the data in the generic cost sheet comes from generic shells and sub-shells. The first two columns are displayed by default. The view is fixed, and there is no split screen capability.
Last Published Sunday, July 20, 2025