Schedule Tab of the Schedule Sheet Properties
The schedule sheet refresh updates cost data associated with the schedule sheet. The refresh updates activity costs and resource/role costs.
A schedule sheet refresh can fail if:
- An activity has more than one CBS code
- A cost sheet column to which a schedule sheet column is associated is deleted from the cost sheet
You can set the refresh frequency. The refresh frequency you set is shown in the schedule sheet log under the column heading Scheduled. Schedule sheets that require refresh are listed in the Schedule Sheet log displaying the refresh icon.
To set the refresh frequency of schedule sheet template data
- Open the project/shell and switch to User mode.
- In the left Navigator, click Schedule Manager > Schedule Sheets.
The Schedule Sheets log open.
- Select one or more schedule sheet templates.
- Choose Refresh > Set Frequency. The Set Frequency window opens.
- Select the Enable scheduled refresh check box.
- Select the Frequency and the Range of Recurrence.
- Click OK.