Create a master schedule sheet

The system allows one master schedule sheet per project/shell. You can mark a schedule sheet in a project or shell and project or shell template as the Master Schedule sheet.

Caution: Upon saving, Master Schedule designation is permanent and cannot be undone.

You can use the master schedule sheet to:

You can mark one schedule sheet in a project/shell as the master schedule sheet.

After you save a schedule sheet as the master, there is no un-do to non-master status.

To mark a sheet as the master schedule sheet

  1. Open the project/shell and switch to User mode.
  2. In the left Navigator, click Schedule Manager > Schedule Sheets.

    The Schedule Sheets log opens.

  3. Select the sheet that you want to make a Master Schedule Sheet and click the Properties button. The Properties window opens on the General tab.
  4. Select the Create as master schedule sheet check box.
  5. Click Yes to confirm.