Working with Schedule Sheets with Scope Management
You can have any number of schedule sheets. There is one master sheet, which appears in bold in the log. The master schedule sheet drives the activity start and finish dates. You can use it to track progress and resource assignment information to other modules. You can use scope management on any schedule sheet. You must have the correct permissions to be able to view and modify scope management data. If you find that you cannot access the functionality that you need, see your company administrator.
To access project schedule sheets
- Go to the project/shell tab and switch to User mode.
- In the left Navigator, click Schedule Manager > Schedule Sheets.
The Schedule Sheets log opens. By default, the log lists all active schedule sheets.
- To view all active and inactive sheets, click the View menu and choose All.
Related Topics
Scope management and multiple calendars
Manage scope management properties
About scope management data elements
Set up scope management for activities
Last Published Sunday, July 20, 2025