Cumulative
Option | 01-09 | 02-09 | 03-09 | 04-09 | 05-09 | 06-09 | 07-09 | 08-09 | 09-09 | 10-09 | 11-09 | 12-09 |
---|---|---|---|---|---|---|---|---|---|---|---|---|
Linear | 1000 | 2000 | 3000 | 4000 | 5000 | 6000 | 7000 | 8000 | 9000 | 10000 | 11000 | 12000 |
S-Curve | 26.52 | 131.40 | 454.46 | 1243.76 | 2705.93 | 4826.86 | 7228.29 | 9349.22 | 10797.07 | 11572.10 | 11895.10 | 11999.99 |
On Start and Finish | 600 | 600 | 600 | 600 | 600 | 600 | 600 | 600 | 600 | 600 | 600 | 12000 |
To set up budget distribution for activities at the activity level
- Go to the project/shell tab and switch to User mode.
- In the left Navigator, click Schedule Manager > Schedule Sheets.
- In the Schedule Sheets log, select a schedule sheet and click Open.
- Select an activity in the sheet.
- From the File menu, select Budget and Progress Setup > Activity.
- Under the Activity Budget Distribution Profile section, choose an option.
This option will apply specifically to the selected activity, and will override any default option set up at the schedule sheet level. The behavior of these Activity Budget Distribution Profile options at the activity level is the same as the default options at the schedule sheet level.
Last Published Sunday, July 20, 2025