% Earned Calculation Method option is Update Activity and all resources on activity start and finish
If the entry method and option settings on the Budget and Progress Method Setup window are:
- % Complete and Earned Progress entry method = Independently Control % complete and earned quantity
- % Complete Calculation Method option = Manual activity % complete and resource % complete
- % Earned Calculation Method option = Update Activity and all resources on activity start and finish
then this data entry method scenario results:
Activity or Resource | Data Element | Data Entry Method | |
Activity | |||
| Activity % Complete | Manual entry | |
Earned Progress | Calculated (Weighted Cost) and read-only. {Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 | ||
Resource | |||
| Progress Quantity | Manual entry | |
Earned Progress | Calculated (read-only) based Update Activity and all resources on activity start and finish. For example: If % earned on Actual Start = 5% and % earned on Actual Finish = 95 % then, when Actual Start is entered, Earned Progress = 5% * Quantity When Actual Finish is entered, Earned Progress = 100% * Quantity. |
Last Published Sunday, July 20, 2025