Activity and resource % complete updates % earned
This section contains scenarios for calculations based on the entry method Activity and Resource % Complete Updates % Earned and the % Complete Calculation Method option selected.
Related Topics
Method is Manual activity % complete and resource % complete
Method is Manual activity % complete - updates resource % complete
Method is Resource updates Activity - weighted avg. of resource hours
Method is Resource updates Activity - weighted avg. of resource costs
Method is Lead resource updates Activity and other resources