Activity and resource % earned updates % complete

This section contains scenarios for calculations based on the entry method Activity % Earned and Resource % Earned Updates % Complete and the % Earned Calculation Method option selected.

Related Topics

Method is Manual activity % earned and resource % earned

Method is Manual activity % earned - updates resource % earned

Method is Resource updates Activity - weighted avg. of resource costs

Method is Lead resource updates Activity and other resources

Method is Update Activity and all resources on start and finish