DS05 Schedule Logic

Note: Relationships to activities outside the set of projects being exported are represented by relationships to placeholder tasks with a subtype of SVT.

CPP Field Name

CPP Field Description

P6 Source

PARSID

Project Assessment and Reporting System identifier for the project submitted.

Entered in the template.

CPP_status_date

Contractor "as-of" date.

Entered in the template.

schedule_type

Describes whether the schedule is a baseline (BL) or forecast (FC).

Project type

task_ID

Task identifier of the successor.

Activity ID (Successor)

predecessor_task_ID

Task identifier of the predecessor.

Activity ID (Predecessor)

type

Determines whether the relationship between task and predecessor is finish to start (FS), start to start (SS), start to finish (SF), or finish to finish (FF)

Relationship Type

lag_days

Task relationship lag, based on predecessor's calendar. A positive figure represents lag, a negative figure represents lead.

Lag

subproject_ID

Unique subproject identifier.

Project Short Name of the predecessor activity's project.