DS06 Schedule Resources

CPP Field Name

CPP Field Description

P6 Source

PARSID

Project Assessment and Reporting System identifier for the project submitted.

Entered in the template.

CPP_status_date

Contractor "as-of" date.

Entered in the template.

schedule_type

Describes whether the schedule is a baseline (BL) or forecast (FC).

Project type

task_ID

Task identifier.

Activity ID (Successor)

resource_ID

Resource identifier.

Resource ID

resource_name

Resource name.

Resource Name

role_ID

Role identifier.

Role ID

role_Name

Role name.

Role Name

type

Resource type.

Resource Type

EOC

Element of cost describes whether the cost associated with the resource is related to labor, subcontract, materials, indirect, or " other direct costs".

Restricted to:

• labor

• material

• ODC

• indirect

• subcontract

This field cannot be empty.

Mapped in the template.

start_date

Resource start date.

Start Date of the assignment.

finish_date

Resource finish date.

Finish Date of the assignment.

budget_dollars

Total budget in dollars.

Planned Cost

actual_dollars

Total actual in dollars.

Actual Cost

remaining_dollars

Total remaining in dollars.

Remaining Cost

budget_units

Total budgeted units.

The units of measure are specified in the UOM field.

 

Planned Units

actual_units

Total actual units.

The units of measure are specified in the UOM field.

Actual Units

remaining_units

Total remaining units.

The units of measure are specified in the UOM field.

Remaining Units

UOM

Unit of measure for budgeted_units, actual_units, and remaining_units fields.

If the resource type is labor or nonlabor, the value of the UOM is "h".

If the resource is a material the value of UOM is derived from the Unit of Measure for the material resource.

If a material unit has not been specified, the value is "units".

lag_planned_days

Task relationship planned lag, based on predecessor's calendar. A positive figure represents lag, a negative figure represents lead.

Planned Lag

lag_remaining_days

Task relationship remaining lag, based on predecessor's calendar. A positive figure represents lag, a negative figure represents lead.

Remaining Lag

calendar_name

The calendar name for the resource or role.

For resource assignments or resources with a role assignment, the resource's calendar is used. For role assignments, the activity calendar is used.

Calendar

subproject_ID

Unique subproject identifier, which can be used for SVT tasks or multi-project schedules.

Project ID