DS06 Schedule Resources
CPP Field Name | CPP Field Description | P6 Source |
---|---|---|
PARSID | Project Assessment and Reporting System identifier for the project submitted. | Entered in the template. |
CPP_status_date | Contractor "as-of" date. | Entered in the template. |
schedule_type | Describes whether the schedule is a baseline (BL) or forecast (FC). | Project type |
task_ID | Task identifier. | Activity ID (Successor) |
resource_ID | Resource identifier. | Resource ID |
resource_name | Resource name. | Resource Name |
role_ID | Role identifier. | Role ID |
role_Name | Role name. | Role Name |
type | Resource type. | Resource Type |
EOC | Element of cost describes whether the cost associated with the resource is related to labor, subcontract, materials, indirect, or " other direct costs". Restricted to: • labor • material • ODC • indirect • subcontract This field cannot be empty. | Mapped in the template. |
start_date | Resource start date. | Start Date of the assignment. |
finish_date | Resource finish date. | Finish Date of the assignment. |
budget_dollars | Total budget in dollars. | Planned Cost |
actual_dollars | Total actual in dollars. | Actual Cost |
remaining_dollars | Total remaining in dollars. | Remaining Cost |
budget_units | Total budgeted units. The units of measure are specified in the UOM field.
| Planned Units |
actual_units | Total actual units. The units of measure are specified in the UOM field. | Actual Units |
remaining_units | Total remaining units. The units of measure are specified in the UOM field. | Remaining Units |
UOM | Unit of measure for budgeted_units, actual_units, and remaining_units fields. | If the resource type is labor or nonlabor, the value of the UOM is "h". If the resource is a material the value of UOM is derived from the Unit of Measure for the material resource. If a material unit has not been specified, the value is "units". |
lag_planned_days | Task relationship planned lag, based on predecessor's calendar. A positive figure represents lag, a negative figure represents lead. | Planned Lag |
lag_remaining_days | Task relationship remaining lag, based on predecessor's calendar. A positive figure represents lag, a negative figure represents lead. | Remaining Lag |
calendar_name | The calendar name for the resource or role. For resource assignments or resources with a role assignment, the resource's calendar is used. For role assignments, the activity calendar is used. | Calendar |
subproject_ID | Unique subproject identifier, which can be used for SVT tasks or multi-project schedules. | Project ID |