CPP Glossary
Abbreviation | Description |
---|---|
# | number |
$RAM | dollarized RAM |
Ac | ACWP cumulative |
Act | actual |
ACWP | actual cost of work performed |
ACWPc | ACWP cumulative |
ACWPi | ACWP incremental |
AF | actual finish |
Ai | ACWP incremental |
AS | actual start |
ASAP | as soon as possible |
ATC | at completion |
auth | authorization |
AUW | authorized unpriced work |
BAC | budget at completion |
BCP | baseline change proposal |
BCR | baseline change request |
BCR-C | BCR usage of contingency |
BCR-M | BCR usage of MR |
BCR-P | BCR usage of UB |
BCWP | budgeted cost for work performed |
BCWPc | BCWP cumulative |
BCWPi | BCWP incremental |
BCWS | budgeted cost for work scheduled |
BCWSc | BCWS cumulative |
BCWSi | BCWS incremental |
bgt | budget |
BL | baseline |
BOM | bill of material |
BWC | base work construct |
c | cumulative |
CA | control account |
CAL | corrective action list |
CAM | control account manager |
CBB | contract budget base |
CC | change control or charge code |
CD | critical decision |
CFSR | contract funds status report |
CI | critical item |
CLIN | contract line item number |
cmp | type of EVMS cost tool software file |
CNT | DOE contingency |
col. | column |
con | contract |
CPP | contractor project performance |
CPP+1 | CPP, 1 month future |
CPP-1 | CPP, 1 month prior |
CPP-2 | CPP, 2 months prior |
CPP-3 | CPP, 3 months prior |
CPP-5 | CPP, 5 months prior |
CPPSD | CPP supporting documentation |
CS | constraint |
csv | comma-separated value |
cum | cumulative |
CV | cost variance |
Cx | commissioning |
D | direct |
DB | distributed budget |
DID | data item descriptions |
DMS | document management system |
DOE | U.S. Department of Energy |
DS | data set |
e.g. | for example |
EAC | estimate at completion |
EACc | EAC cumulative |
EACi | EAC incremental |
EE | Office of Energy Efficiency and Renewable Energy |
EF | early finish |
EFCO | Energy Facility Contractors Group |
EIA | Electronic Industries Alliance |
EM | Office of Environmental Management |
EOC | element of cost |
ES | early start |
est | estimate |
ETC | estimate to complete |
ETCc | ETC cumulative |
EU | estimate uncertainty |
EV | earned value |
EVM | earned value management |
EVMS | earned value management system |
EVT | earned value technique |
F | format |
F | FTE |
fav | favorable |
FC | finish constraint |
FC | forecast |
FE | Office of Fossil Energy |
FF | finish to finish |
FF | flat file |
FFTSCS | flat file to source crosswalk spreadsheet |
FIFO | first-in, first-out |
FS | finish to start |
FY | fiscal year |
GAO | U.S. Government Accountability Office |
GL | guideline |
H | hours |
HDV | high dollar value |
I | indirect |
i.e. | that is |
ID | identifier |
IMP | integrated master plan |
IMS | integrated master schedule |
inc | incremental |
IP2M | integrated project/program management |
IPMR | integrated program management report |
JSON | JavaScript object notation |
K | thousands of dollars |
ktr | contractor |
LF | late finish |
LIFO | last-in, first-out |
LOE | level of effort |
LS | late start |
M | milestone |
M | month |
max. | maximum |
METRR | maturity and environment total risk rating |
MF | finish milestone |
MIN or min. | minimum |
MR | management reserve |
MS | start milestone |
NA | National Nuclear Security Administration |
NA or N/A | not applicable |
NCC | negotiated contract cost |
NDIA | National Defense Industrial Association |
NE | Office of Nuclear Energy |
neg | negotiated |
no | number |
NTE | not-to-exceed |
O | order |
OBS | organization breakdown structure |
ODC | other direct costs |
OE | Office of Electricity |
org | original |
OTB | over-target baseline |
OTS | over-target schedule |
P | period |
PARS | Project Assessment and Reporting System |
PASEG | Planning & Scheduling Excellence Guide |
PB | performance baseline |
PBB | project budget base |
Pc | BCWP cumulative |
PC | percent complete |
pct | percent |
PEP | project execution plan |
perf | performance |
Pi | BCWP incremental |
PM | contractor project manager |
PM | Office of Project Management |
PMB | performance measurement baseline |
PMP | project management plan |
PO | purchase order |
POC | point of contact |
POP | period of performance |
PP | planning package |
PRJ | project summary |
QBD | quantity basis document |
QRA-CL | quantitative risk analysis confidence level |
qty | quantity |
RAM | responsibility assignment matrix |
RC | root cause |
RD | resource dependent |
R&D | research and development |
rel | relationship |
rem | remaining |
rep | representative |
req'd | required |
RMT | risk mitigation task |
RP | reporting period |
RP | reporting period date (the associated CPP status date) |
RP+1 | next RP |
RPG | formal reprogramming analysis |
rpg | reprogramming adjustment |
RPT | report |
SC | Office of Science |
SC | schedule contingency |
SC | start contraint |
SD | system description |
SF | start to finish |
SLPP | summary level planning package |
SM | schedule margin |
SOP | standard operating procedure |
SOW | scope of work |
SR | schedule reserve |
SS | start to start |
SU | start-up |
subK | subcontract |
subktr | subcontractor |
SV | schedule variance |
SVT | schedule visibility task |
TAB | total allocated budget |
TCPI | to-complete performance index |
TD | task dependent |
tgt | target |
tot | total |
UB | undistributed budget |
UCNI | unclassified controlled nuclear information |
unfav | unfavorable |
UOM | unit of measure |
v | version |
VAC | variance at completion |
VAR | variance |
W | whole dollars |
w/ | with |
w/o | without |
WAD | work authorization document |
WBS | work breakdown structure |
WP | work package |
WPM | WP manager |
WS | WBS summary |
X | numerator value or test flags |
xer | type of IMS software file |
Y | denominator value or test population |
ZBA | zero budget activity |