DS20_schedule_calendar_exception

CPP Field Name

CPP Field Description

P6 Source

calendar_name

Unique calendar name.

Align with DS21.calendar_name.

Calendar Name

exception_date

Date of exception

Associated calendar

exception_work_day

Determines whether the exception is a non-work day. If the exception is a work day, this field shows N. If it is a non-work day the field shows Y and shifts do not need to be provided.

Associated calendar

exception_shift_A_start_time

Exception shift A start time, according to the associated calendar.

Start Time for first shift on the day according to the exceptions in the associated calendar

exception_shift_A_stop_time

Exception shift A finish time, according to the associated calendar.

Finish Time for first shift on the day according to the exceptions in the associated calendar

exception_shift_B_start_time

Exception shift B start time, according to the associated calendar.

Start Time for second shift on the day according to the exceptions in the associated calendar

exception_shift_B_stop_time

Exception shift B finish time, according to the associated calendar.

Finish Time for second shift on the day according to the exceptions in the associated calendar

exception_shift_C_start_time

Exception shift C start time, according to the associated calendar.

Start Time for third shift on the day according to the exceptions in the associated calendar

exception_shift_C_stop_time

Exception shift C finish time, according to the associated calendar.

Finish Time for last shift on the day according to the exceptions in the associated calendar