DS20_schedule_calendar_exception
CPP Field Name | CPP Field Description | P6 Source |
---|---|---|
calendar_name | Unique calendar name. Align with DS21.calendar_name. | Calendar Name |
exception_date | Date of exception | Associated calendar |
exception_work_day | Determines whether the exception is a non-work day. If the exception is a work day, this field shows N. If it is a non-work day the field shows Y and shifts do not need to be provided. | Associated calendar |
exception_shift_A_start_time | Exception shift A start time, according to the associated calendar. | Start Time for first shift on the day according to the exceptions in the associated calendar |
exception_shift_A_stop_time | Exception shift A finish time, according to the associated calendar. | Finish Time for first shift on the day according to the exceptions in the associated calendar |
exception_shift_B_start_time | Exception shift B start time, according to the associated calendar. | Start Time for second shift on the day according to the exceptions in the associated calendar |
exception_shift_B_stop_time | Exception shift B finish time, according to the associated calendar. | Finish Time for second shift on the day according to the exceptions in the associated calendar |
exception_shift_C_start_time | Exception shift C start time, according to the associated calendar. | Start Time for third shift on the day according to the exceptions in the associated calendar |
exception_shift_C_stop_time | Exception shift C finish time, according to the associated calendar. | Finish Time for last shift on the day according to the exceptions in the associated calendar |