Primavera Unifier tab - Project Details (P6 EPPM Only)

Use this tab to link a P6 Professional project with a Primavera Unifier project and schedule sheet or summary sheet and to select the mapping definition that will be used during the update.

Schedule Sheet Integration Section

Allow this project to link with a Primavera Unifier Project: Mark to link the open project with a Primavera Unifier project.

Project Name: The name of the Primavera Unifier project. To select a project, click  .

Schedule Sheet: The name of the Primavera Unifier schedule sheet for the selected project. To select a schedule sheet, click  .

Data Mapping: The name of the data mapping defined for the selected schedule sheet. To select a data mapping, click  .

Delete from Primavera Unifier any activities no longer in the P6 Schedule: Mark to enable P6 to remove deleted activities.

Only send activities with CBS codes assigned: Mark to only send P6 Professional activities with CBS codes assigned to Primavera Unifier. If you mark this option, relationships will not be sent to the Schedule Sheet.

Summary Sheet Integration Section

Schedule Type: The type of schedule data to send to Primavera Unifier.

Synchronize WBS Hierarchy: Mark to specify that the WBS hierarchy should be sent to Primavera Unifier. If you do not send WBS hierarchy data to Unifier, only summary and spread data will be sent.

Levels: Set the number of WBS levels to synchronize.

Note: You must set up Primavera Gateway integration on the Application Settings page in P6 before you can connect P6 Professional to a Primavera Unifier summary sheet.