Project Complexity
A project's complexity value can be between 0 and 100. If the project complexity value equals 0, P6 Professional uses the low estimate for each activity. If the project complexity value equals 100, P6 Professional uses the high estimate for each activity. For project complexity values between 0 and 100, P6 Professional calculates an intermediate value between the low and high estimates for each activity. The value calculated using the project complexity factor is then copied into the budgeted or planned labor/ nonlabor units and expense costs for each activity.