Enabling Daily History Snapshots and Slowly Changing Dimensions
To enable SCDs and daily history snapshots for a P6 project:
- Sign in to P6 EPPM.
http://<host>:<port>/p6/action/login
- In P6, click Projects.
- On the Projects screen navigation bar, click EPS.
- On the EPS page:
- Select a project.
- From the Row Actions menu of the selected project, select Set Project Preferences.
- In the Project Preferences pane:
- Ensure the project is configured for publication services.
- Click the Analytics & Services tab.
- Select the Enable Publication option in the Publication section.
- Configure the project's History Level setting.
- Click the Analytics & Services tab.
- From the History Level list, select Activity (Daily), Activity (Weekly) or Activity (Monthly).
Note: You should still configure the History Interval setting, but it will only apply to Project and WBS-level history metrics.
- Click Save and Close.
- Ensure the project is configured for publication services.