Configuring P6 Codes for each Data Source
To extract and load a subset of P6 EPPM codes:
- Sign in to Primavera Analytics Administration application:
http://<host>:<port>/p6rdb
- In the sidebar, select Status.
- In the All list, select staretl<id> or a <custom name for data source>.
- In the left pane, select Codes.
- To migrate codes for the selected P6 data source, select any of the following tabs:
- Project
- Activity
- Notes:
- A maximum of 240 codes is supported for each area (Project, Activity, and Resource).
- By default, only those codes that have been enabled through the Primavera Analytics Administration application are exposed in the subject areas.
- To select codes for migration:
- From the Available Codes list, select one or more P6 codes.
- Select Move Right.
- To deselect codes from being migrated:
- From the Enabled Codes list, select one or more P6 codes you want to remove.
- Select Move Left.
- Select Save.