Auto-Scheduling
If the user clicks on Update > Linked Schedule Sheets, only the Activity Data will get updated on the destination (linked) Schedule Sheets from the template, and not the sheet properties.
- If Auto-scheduling is enabled in the Linked (destination) Schedule Sheet, then after the Activity Dates update through Update> Linked Schedule Sheets, the re-scheduling will take place.
- If Auto-scheduling is disabled in the Linked (destination) Schedule Sheet, then only the Activity Dates is updated and no re-scheduling occurs. That is to state that the change will be reflected in dependent activities.