Summary Payment Applications (SOV Structure)

To update the destination shell templates with Summary Payment Applications setup:

  1. Go to the Company Workspace tab and switch to Admin mode.
  2. In the left Navigator, click Templates > Shells > Projects.
  3. From the Projects Templates log, select and open a project.
  4. From the navigation pane, click Cost Manager to expand it, click Schedule of Values to expand it, and click Summary Payment Applications to expand it. Select the desired SOV functional sub-node.
  5. In the Schedule of Values: Summary Payment Applications log, from the toolbar, click Update Shell Templates to open the Update Shell Templates menu items. Your options are as follows:
    • Shells Templates
    • All Other Shell Templates
    • History

The following explores each option in detail.

Shells Templates

If you select this option, then the Select Shell Templates window opens that displays a list of projects that you can select. The projects are listed in the Projects log, and the details of each project are displayed in columns:

Select from the projects that you want to update and from the toolbar click Update. When the Confirmation window opens, review the message that is displayed in the Confirmation window.

Update Shell Templates with Commitment Funding Sheet Structure

- Structure will be added if does not exist

- Structure will be replaced if does exist

This will update shell templates and cannot be reverted. Do you want to continue?

Click Yes, if you want to update the selected shell templates, or click No, to cancel your update.

If you click Yes, then the push job gets initiated and the History log will show the job details.

The Commitment Funding Sheet setup will be added or replaced in the destination shell templates.

The History log will show the job details.

All Other Shell Templates

If you select this option, then a Confirmation window opens with the following message:

Update Shell Templates with Commitment Funding Sheet Structure

- Structure will be added if does not exist

- Structure will be replaced if does exist

This will update shell templates and cannot be reverted. Do you want to continue?

Click Yes, if you want to update all of the shell templates, or click No, to cancel your update.

History

If you click the History menu item, then the Shell Template History window opens. This window shows the details of the submitted update requests. This window has the following columns:

The History log provides details of each job by showing the actions performed as a part of Summary Payment Applications setup push to the destination shell templates.

In the case where in certain shell templates the job is not successful, the history details lists the shell templates where the update has failed and displays the reason for the failure.

You can select an item in the list and click Open, from the toolbar, to see the details about that item.

You have the option to click the Cancel Request option, from the toolbar, if the request is not in progress or has not been completed.

See Also

Updating Shell Templates

Access Control

Business Process and Workflow Setups

Gates

Dashboards

Rules

Cash Flow

Cost Sheet Columns

Commitment Funding Sheet

Document Manager

General Spends (SOV Structure)

Payment Applications (SOV Structure)

Reports (User-Defined Reports)

Activity Sheets



Last Published Thursday, December 14, 2023