How to Set Up Gates

Before you begin: Verify that the list of phases resides in the Phase data definition drop-down (pull-down) data set. This is the same list that is used when selecting a phase manually in the shell properties window. You can add or modify the default list as needed. This list makes the phases available for any shell instance or shell type template; for each shell or template, you select which of the phases to use. Create any business processes that you plan to use to drive gates conditions and phase completion.

Step 1: Define Phases. For each shell instance or shell type template, you define the list of phases to include in the setup, choosing from the entire list in the Phase data set.

Step 2: Define Gate Conditions. For each phase, define one or more gate conditions. A gate condition is a combination data element and trigger condition that enable transition to the next phase.

Step 3: Schedule Gates runs. The gates run the validation of gate conditions. You can schedule runs automatically. This is optional.

Step 4: Activate the Gates setup.

Step 5: Define permissions.

Notes:

In This Section

Example of a Gates Setup and Conditions

Define the Phase List

Create a Gates Setup

Delete a Gates Setup

Add Phases to the Gates Setup (Settings Tab)

Access Gate Configuration View

Configure Gate Elements

Change the Order of Phases

Define Gates Runs Schedule (Schedule Tab)

Activate or Deactivate a Gates Setup

Set User Permissions for Gates