ResourceAssignmentUpdated Message
Field | Type | Description |
---|---|---|
ActivityObjectId | int | The unique ID of the activity to which the resource is assigned. |
CostAccountObjectId | int | The unique ID of the cost account associated with this resource assignment. |
ObjectId | int | The unique ID generated by the system. |
ProjectObjectId | int | The unique ID of the associated project. |
ResourceObjectId | int | The unique ID of the associated resource. |
RoleObjectId | int | The unique ID of the role the resource is performing on this activity. A resource may be assigned to the same activity more than once, performing different roles. The project manager controls whether the same resource can be assigned to an activity more than once. |
NewValues | ResourceAssignmentType Refer to the entries in the ResourceAssignmentType Table below. Additional information can be found in the p6events.xsd schema. | The new values of Physical and writable fields that have changed. |
OldValues | ResourceAssignmentType Refer to the entries in the ResourceAssignmentType Table below. Additional information can be found in the p6events.xsd schema. | The old values of Physical and writable fields that have changed. |
ResourceAssignmentType Table
Type: ResourceAssignmentType | |
Elements | Type |
ActivityObjectId | int |
ActualCost | double |
ActualCurve | string |
ActualFinishDate | dateTime |
ActualOvertimeCost | double |
ActualOvertimeUnits | double |
ActualRegularCost | double |
ActualRegularUnits | double |
ActualStartDate | dateTime |
ActualThisPeriodCost | double |
ActualThisPeriodUnits | double |
ActualUnits | double |
AtCompletionCost | double |
AtCompletionUnits | double |
CostAccountObjectId | int |
DrivingActivityDatesFlag | boolean |
IsActivityFlagged | boolean |
IsCostUnitsLinked | boolean |
ObjectId | int |
OvertimeFactor | double |
PendingPercentComplete | double |
PendingRemainingUnits | double |
PlannedCost | double |
PlannedCurve | string |
PlannedFinishDate | dateTime |
PlannedLag | double |
PlannedStartDate | dateTime |
PlannedUnits | double |
PlannedUnitsPerTime | double |
Proficiency | string |
RateSource | string |
RateType | string |
RemainingCost | double |
RemainingCurve | string |
RemainingFinishDate | dateTime |
RemainingStartDate | dateTime |
RemainingUnits | double |
RemainingUnitsPerTime | double |
ResourceCurveObjectId | int |
ResourceObjectId | int |
ResourceType | string |
RoleObjectId | int |
Last Published Monday, November 27, 2023