CopyBaselineInvoked Method
| Field | Type | Description | 
|---|---|---|
| NewBaselineProjectObjectId | int | The project id generated for the newly created baseline. | 
| SourceProject | SourceProjectType Refer to the entries in the SourceProjectType table below. | The complex element that identifies the source project from which the baseline was copied. | 
| TargetEPS | TargetEPSType Refer to the entries in the TargetEPSType table below. | The complex element that identifies the target EPS under which the baseline was copied. | 
| Status | JobStatusType Refer to the entries in the JobStatusType table below. | Describes the state of the job after completion. | 
SourceProjectType Table
| SourceProjectType | |
| Id | string | 
| Name | string | 
| ProjectObjectId | ObjectId | 
TargetEPSType Table
| TargetEPSType | |
| Id | string | 
| Name | string | 
| ProjectObjectId | ObjectId | 
| WBSObjectId | ObjectId | 
JobStatusType Table
| JobStatusType | 
|---|
| string restricted to completed or failed. | 