Interface Change Details

The following table provides an overview of updated field lengths, updated values, new fields, and new enumerations.

WSDL

Field Level Changes

Release

Document.wsdl

The maxLength of the PrivateLocation field has increased to 4000.

The maxLength of the PublicLocation field has increased to 4000.

23.4

Export.wsdl

The following new operations have been added:

  • ExportCppProject
  • ExportXERProject

The following fields have been added to the Project field list of BusinessObjectOptions:

  • TeamMemberCanOutOfSequenceFlag
  • TeamMemberDisplayDiscussionsFlag

The following field has been added to the Relationship field list of BusinessObjectOptions:

  • PredCalendarObjectId

The following field has been added to the WBS field list of BusinessObjectOptions:

  • PhaseName

The following value has been added to the string restrictions of the FileType field of the ExportProject operation:

  • XER

23.4

Import.wsdl

The following value has been added to the string restrictions of the FileType and ImportType fields of the ImportProject operation:

  • XER

The following options have been added to the Global field list of the BusinessObjectOptions field of the CreateNewProject Operation:

  • DocumentCategory
  • DocumentStatusCode

The following option has been added to the ProjectSpecific field list of the BusinessObjectOptions field of the CreateNewProject Operation:

  • Document

The following field has been added to the ImportProject Type Table of the ImportProjects Operation:

  • FinancialPeriodCalendarObjectId

23.4

Job.wsdl

The following input elements have been added to the SummarizeProject Operation:

  • PortfolioObjectId
  • ProjectCodeObjectId

The following input element has been added to the Schedule Operation:

  • ProjectCodeObjectId

The following input elements have been added to the Level Operation:

  • EPSObjectId
  • PortfolioObjectId
  • ProjectCodeObjectId

The following input elements have been added to the Apply Actuals Operation:

  • EPSObjectId
  • PortfolioObjectId
  • ProjectCodeObjectId

23.4

Project.wsdl

The following fields have been added to Project fields:

  • TeamMemberCanOutOfSequenceFlag
  • TeamMemberDisplayDiscussionsFlag

23.4

Relationship.wsdl

The following field has been added to Relationship Fields:

  • PredCalendarObjectId

23.4

ResourceAssignmentUpdate.wsdl

The following field has been added to ResourceAssignmentUpdate fields:

  • LastApprovedDate

23.4

Currency.WSDL

The following field has been added to Currency fields:

  • UpdateResourceRates

23.10

Export.wsdl

The following field has been added to the WBS field list of BusinessObjectOptions:

  • PhaseName
  • The following field has been added to the Project field list of BusinessObjectOptions:
  • TeamMemberProjectViewableFields

23.10

Import.wsdl

The following field has been added to the CreateNewProject Operation:

  • FinancialPeriodCalendarObjectId

The JobObjectId field in the ImportProjectAsyncASAP Response in the ImportProjectAsyncASAP Operation has changed type from int to string.

23.10

Job.wsdl

The following operation has been added to the Job Service:

  • Publish

23.10

JobService.wsdl

The following enumeration has been added to the JobType field of JobService Fields:

  • Schedule Publish Project

23.10

Project.wsdl

  • The following field has been added to Project Fields:
  • TeamMemberProjectViewableFields

23.10

ResourceAccess.wsdl

The following field has been added to ResourceAccess Fields:

  • ResourceAccess

23.10

WBS.wsdl

The following field has been added to WSB Fields:

  • Phase

23.10

See Also

What's New In P6 EPPM Web Services

What's Changed in this Release



Last Published Friday, February 9, 2024