Project Schedule Task
P6 EPPM Field | UN/CEFACT Field |
---|---|
Name | Description |
ObjectId | ID |
WBS_+WBSObjectId | DataNodeID |
ActivityId+Name | Description |
UDF/Code | RiskLevelDescription |
Percent Complete | CalculatedCompletionPercent |
Physical Percent Complete | AssessedCompletionPercent |
UDF | PriorityRankingNumeric |
UDF/Code | EarnedValueMethodCode |
UDF | ScheduleLevelNumeric |
Free Float | FreeFloatDurationMeasure |
Total Float | TotalFloatDurationMeasure |
UDF | MilestoneWeightNumeric |
Activity Type | TypeCode |
Actual Duration | TotalDurationMeasure |
Remaining Duration | RemainingDurationMeasure |
Is Critical | CriticalPathIndicator |
UDF/Code | ControlAccountID |
UDF/Code | ScheduleLevel |
Planned Duration (P6 EPPM) Original or Planned Duration (P6 Professional) | OriginalDurationMeasure |
Baseline Duration | BaselineDurationMeasure |
Minimum Duration or UDF | BestCaseDurationMeasure |
Most Likely Duration or UDF | MostLikelyDurationMeasure |
Maximum Duration or UDF | WorstCaseDurationMeasure |
Finish Date Variance | FinishVarianceDurationMeasure |
Start Date Variance | StartVarianceDurationMeasure |
UDF/Code | WorkPackageID |
TaskObjectId | SourceID |
ProjectObjectId | ProjectID |
UDF/Code | PlanningLevelCode |
CalendarObjectId | ScheduleProjectScheduleCalendar.ProjectScheduleCalendar.ID |
Early Start Date, Late Start Date | CurrentScheduledBasePeriod.BasePeriod.StartDateTime |
Early Finish Date, Late Finish Date | CurrentScheduledBasePeriod.BasePeriod.EndDateTime |
Value ='early','late' | CurrentScheduledBasePeriod.BasePeriod.Description |
Actual Start Date | ActualScheduledBasePeriod.BasePeriod.StartDateTime |
Actual Finish Date | ActualScheduledBasePeriod.BasePeriod.EndDateTime |
Planned Start Date | TargetScheduledBasePeriod.BasePeriod.StartDateTime |
Planned Finish Date | TargetScheduledBasePeriod.BasePeriod.EndDateTime |
Early Start Date, Late Start Date | ResourceScheduledBasePeriod.BasePeriod.StartDateTime |
Early Finish Date, Late Finish Date | ResourceScheduledBasePeriod.BasePeriod.EndDateTime |
Value ='early','late' | ResourceScheduledBasePeriod.BasePeriod.Description |
UDF | BestCaseScheduledBasePeriod.BasePeriod.StartDateTime |
UDF | BestCaseScheduledBasePeriod.BasePeriod.EndDateTime |
Value ='early','late' | BestCaseScheduledBasePeriod.BasePeriod.Description |
UDF | MostLikelyScheduledBasePeriod.BasePeriod.StartDateTime |
UDF | MostLikelyScheduledBasePeriod.BasePeriod.EndDateTime |
Value ='early','late' | MostLikelyScheduledBasePeriod.BasePeriod.Description |
UDF | WorstCaseScheduledBasePeriod.BasePeriod.StartDateTime |
UDF | WorstCaseScheduledBasePeriod.BasePeriod.EndDateTime |
Value ='early','late' | WorstCaseScheduledBasePeriod.BasePeriod.Description |
Expected Finish Date | EstimatedScheduledBasePeriod.BasePeriod.EndDateTime |
Baseline Start Date | BaselineScheduledBasePeriod.BasePeriod.StartDateTime |
Baseline Finish Date | BaselineScheduledBasePeriod.BasePeriod.EndDateTime |
Value ='early' | BaselineScheduledBasePeriod.BasePeriod.Description |
Primary Constraint Date, Secondary Constraint Date
| LimitingScheduleTaskTimingConstraint.ScheduleTaskTimingConstraint.LimitDateTime |
Primary Constraint Type,
| LimitingScheduleTaskTimingConstraint.ScheduleTaskTimingConstraint.TypeCode |
Activity Notebook Topic | UserDefinedProjectNote.ProjectNote |