Viewing the ERP Sync Status Field

The ERP Sync Status field is set during the synchronization process to one of the following values:

To view the ERP Sync Status field:

  1. Click Projects.
  2. On the Projects navigation bar, click EPS.
  3. On the EPS page, click Customize View.
  4. In the Manage Views dialog box:
    1. Click the Columns tab.
    2. Expand Project Codes in the Available Columns list and double-click ERP Sync Status to add it to the Selected Columns list.
    3. Click Apply.