Assigning Resource Curves to Resource or Role Assignments from the Resources Assignments Page

You can assign a resource distribution curve to any resource or role assignment on activities with a duration type of Fixed Duration and Units/Time or Fixed Duration & Units.

To assign a resource curve:

  1. Click Resources.
  2. On the Resources navigation bar, click Assignments.
  3. On the Assignments page:
    1. Display the Curves column if it is not visible on the table. To display the Curves column, click Customize View and click Columns, expand the General grouping and double-click Curve to move it to the Selected Columns list.
    2. On the Assignments page:
      • Click the row with the resource or role.
      • Double-click the Curve field, and clickSelect .
    3. In the Select Curves dialog box, choose a curve and click OK.
    4. On the Assignments page, click Save.

Tips:

Related Topics

Defining Resources and Roles

About Roles

Creating Roles

Assigning a Resource to a Role

Assigning a Role Team to a Role

About Role Teams

Creating Role Teams

Assigning a Role to a Role Team

About Resources

Adding Resources

Assigning a Role to a Resource

Assigning a Resource Team to a Resource

Configuring Resource Settings

Assigning Calendars to Resources

Configuring Timesheet Reporting for Resources

Assigning Resource Codes

Assigning Resource Rates

Assigning Role Codes

About Resource Teams

Creating Resource Teams

Assigning a Resource to a Resource Team

Assigning Resource Curves to Resource or Role Assignments from the Activities Page



Last Published Thursday, February 1, 2024