Recalculating Assignment Costs

Recalculate assignment costs to update price per time values on activities. This ensures that project costs reflect any updates.

To recalculate assignment costs:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page:
    1. Select an activity.
    2. Click Actions and select Recalculate Assignment Costs.
    3. In the Recalculate Assignment Costs dialog box:
    4. (Optional) Select the Synchronize overtime factor while recalculating costs option to synchronize the overtime factor defined for each resource when recalculating costs.
    5. Click Recalculate.

Tips

Related Topics

About the Recalculate Assignment Costs Feature



Last Published Thursday, February 1, 2024