Checking for and Resolving Overallocated Resources

Run the Check Resource Overallocation service to identify where resource demand exceeds availability. You can resolve overallocation by adjusting the Remaining Units/Time on the assignment, changing the Start or Finish date on the assignment, or by selecting a different role or resource. On the Assignments page in the Projects section you can also resolve overallocation by adjusting the remaining units on the assignment.

Notes:

To run the Check Resource Overallocation service:

  1. Click Projects.
  2. On the Projects navigation bar, click Assignments.
  3. On the Assignments page, select Check Overallocation.
  4. In the Check Resource Overallocation dialog box:
    1. Select a date to begin the overallocation check.
    2. Select the number of months to include in the overallocation check.
    3. Click Run.
  5. After the service has completed, select Views and then select Overallocated Resources.

Tips

Related Topics

About the Check Resource Overallocation Service

Working with the Check Resource Overallocation Service