Assigning Predecessor Relationships

You can assign predecessor relationships to the activities in a project.

To assign a predecessor relationship:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
    1. On the Activities page, select the activities to which you want to assign predecessors.
    2. Click Row Actions and select Assign Predecessors.
    3. In the Assign Relationships panel:
      • Select one or more activities from the Assign Predecessors list and click Assign Predecessors.
      • Click Close.
    4. On the Activities page, click Save.

Tips

Related Topics

About Relationships

About Relationship Lines

Creating Activity Relationships

Configuring Activity Relationships

Configuring Predecessor Relationships

Assigning Successor Relationships

Configuring Successor Relationships