Assigning Resources to an Activity

Perform these steps to assign one or more resources to an activity.

To assign resources to an activity:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page, select an activity and click the Assignments detail window.
    1. In the Assignments detail window, click Assign... and select Resource.
    2. In the Select a Resource dialog box:
      • Select one or more resources.

        Note: Click Show Usageto show the usage spreadsheet and histogram for the selected resource and optionally change the Start and Finish fields to customize the visible portion of the usage chart. The usage spreadsheet and histogram show the first resource you selected if you select multiple resources.

      • Click Assign.
    3. Confirm whether you want to send an email notification to the affected resources.

Tips

Related Topics

About Resource Assignments

Configuring Activity Resources

Specifying Resource Assignment Rates

Adding Activity Resource Estimates



Last Published Thursday, February 1, 2024