Updating the Progress of Activities Using P6

Update status to define percent complete and start and finish dates.

To update status:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
    1. On the Activities page, select an activity and click the Status detail window.
    2. In the Status detail window:
      • Select or clear the Started and Finished options.
      • If you select an option, click Select Date and select a date from the calendar.
      • Enter a percentage in the Activity % Complete field.
    3. Click Save.

Tips:

Related Topics

About Activity Progress