Applying Actuals to a Project

Apply actuals to update progress on the currently selected projects as of the specified data date.

To apply actuals:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page:
    1. Click Actions and select Apply Actuals.
    2. In the Apply Actuals dialog box:
      • Select the projects to which you want to apply actuals.
      • Select a date from the New Data Date calendar.
      • Select an option from the Remaining Duration Calculation list.
      • Click Apply.

Tips

Related Topics

About The Apply Actuals Feature

Working with the Apply Actuals Feature