Placing or Removing a Hold Team Member Status Updates
To place or remove a hold on status updates:
- Click Approvals.
- On the Approvals navigation bar, select Status Updates.
- On the Status Updates page:
- To place a hold:
- Select Pending.
- On the status update card, select Hold.
- To remove a hold:
- Select Held.
- On the status update card, select Remove hold.
- To place a hold:
Tips
- Pending updates for a project checked out in P6 Professional or opened exclusively are not displayed until the project is checked in or the exclusive lock is released.
- Team members can continue to make updates to activities that have not been approved yet or are on hold. The status updates will reflect the latest team member updates.
Related Topics
Reviewing Team Member Status Updates
Accepting Team Member Status Updates
Rejecting Team Member Status Updates
Overriding Team Member Status Updates
Configuring P6 Team Member Status Update Reviews
Configuring P6 Team Member View Preferences
Last Published Wednesday, July 10, 2024