Earned Value Detail Window of the Assignments Page
Overview
Use this detail window to view the earned value fields for the selected resource assignment.
Screen Elements
Assignment % Complete field
The percent complete for the assignment. The calculation of this field depends on the percent complete type for the activity.
If the activity's percent complete type is Units % Complete and the assignment is in progress, this field is equal to the Units % Complete for the activity. If the assignment is not started, the Units % Complete for the assignment is zero. If the assignment is completed, the Units % Complete is 100%. If the assignment is completed and the actual units are zero, the Units % Complete is zero.
If the activity's percent complete type is Duration % Complete, this field is calculated as (Planned Duration of the assignment - Remaining Duration of the assignment) / Planned Duration of the assignment.
If the activity's percent complete type is Physical % Complete, this field is equal to the Physical % Complete for the activity.
If the activity's percent complete type is Scope % Complete, this field is equal to the Scope % Complete for the activity.
Earned Value Units field
The portion of baseline assignment units that are complete as of the project data date.
Calculated as Budget At Completion Units multiplied by Performance Percent Complete. The method for computing performance percent complete depends on the Earned Value technique selected for the activity's WBS.
Earned Value field
The portion of the baseline total cost of the assignment that is actually completed as of the project data date.
Budget at completion is calculated from the baseline.
Calculated as Budget At Completion multiplied by Performance Percent Complete. The method for computing performance percent complete depends on the Earned Value technique selected for the activity's WBS.
Budget at Completion Units field
The planned total units or at completion units for the resource assignment taken from the baseline project.
Budget at Completion field
The planned total cost or at completion cost for the resource assignment taken from the baseline project.
Estimate to Complete Units field
The estimated units to complete the assignment.
Calculated as either the Remaining Total Cost for the assignment, or as Performance Factor multiplied by (Budget At Completion minus Earned Value), depending on the earned-value technique selected for the activity's WBS. Budget at completion is calculated from the project baseline.
Estimate to Complete field
The estimated cost to complete the assignment.
Calculated as either the Remaining Total Cost for the assignment, or as Performance Factor multiplied by (Budget At Completion minus Earned Value), depending on the earned-value technique selected for the activity's WBS. Budget at completion is calculated from the project baseline.
Getting Here
- Click Projects or Resources.
- On the Projects or Resources navigation bar, click Assignments.
- Select an assignment and click the Earned Value detail window.