Configuring Project Preferences for Multiple Projects

If you need to make changes to the preference for multiple projects simultaneously, you can make the change to the highest relevant EPS node. All changes you make to the fields, options, and lists in the project preferences dialog box at EPS level will be applied to all visible child projects in all visible child EPS nodes of the selected EPS node.

To change project preferences for multiple projects:

  1. Click Projects.
  2. On the Projects navigation bar, click EPS.
  3. Select an EPS node.
  4. Click the Row Actions menu and select Set Project Preferences.
  5. In the Project Preferences of EPS dialog box:
    1. Make the changes you want to apply to child projects.
    2. Click Apply.

Note: Only the preferences you edited will be applied to child projects.

  1. Click Save.

Tips

Related Topics

Configuring Project Preferences

Configuring History Settings for Analytics

Configuring Project Calculations

Configuring Project Defaults

Configuring Project Summarization and Publication Services

Configuring P6 Team Member Status Update Reviews

Configuring P6 Team Member View Preferences

Running the Project Checker