Links to Closed Projects - Activities with links to closed projects Section of the Schedule Check Report Dialog Box
Overview
Use this section to view the activities that have predecessors or successors in projects that were not open when the Check Schedule job was initiated.
Screen Elements
Predecessor Project ID field
The identifying code for the project containing the predecessor activity that failed the check. An asterisk indicates this project was not open when the Check Schedule job was initiated. Click this link to view the predecessor project if it is currently open.
Predecessor Activity ID field
The identifying code for the predecessor activity that failed the check. Click this link to view the predecessor activity.
Predecessor Activity Description field
The brief description of the predecessor activity. Click this link to view the predecessor activity.
Relationship Type field
The type of relationship between two activities.
Valid values are:
Finish to Start: The successor activity cannot start until its predecessor finishes.
Finish to Finish: The successor activity cannot finish until its predecessor finishes.
Start to Start: The successor activity cannot start until its predecessor starts.
Start to Finish: The successor activity cannot finish until its predecessor starts.
Lag Duration (hours) field
The time in hours between the start or finish of the activity and the start or finish of the predecessor successor.
Successor Project ID field
The identifying code of the project that contains the successor activity. An asterisk indicates this project was not open when the Check Schedule job was initiated. Click this link to view the successor project if it is currently open.
Successor Activity ID field
The identifying code of the successor activity. Click this link to view the successor activity.
Successor Activity Description field
The brief description of the successor activity. Click this link to view the successor activity.
Getting Here
- Click Projects.
- On the Projects navigation bar, click Activities.
- Click the Actions
menu and select Check Schedule, then select View Report.
- Click the Actions
Last Published Wednesday, July 10, 2024