Assign Relationships Panel
Overview
Use this panel to configure predecessor and successor relationships for the selected activities.
Screen Elements
Assign Predecessors section
Search
Searches the view or dialog box for data matching the criteria entered into the box.
Project / WBS / Start / Finish button Project / WBS / Start / Finish button
Groups the grid by Project, WBS, activity start date, or activity finish date.
Remove Predecessors
Removes the relationships to the selected predecessor activities.
Assign Predecessors
Creates Finish to Start relationships to the selected activities.
Row Actions menu
Expand All: Expands all grouping bands in the grid.
Collapse All: Collapses all grouping bands in the grid.
ID/Code field
The unique identifier of the activity or WBS.
Name field
The name of the activity or WBS.
Separator control
Moves the separator between the sections of the page.
Assign Successors section
Search
Searches the view or dialog box for data matching the criteria entered into the box.
Project / WBS / Start / Finish button Project / WBS / Start / Finish button
Groups the grid by Project, WBS, activity start date, or activity finish date.
Remove Successors
Removes the relationships to the selected successor activities.
Assign Successors
Creates Finish to Start relationships to the selected activities.
Row Actions menu
Expand All: Expands all grouping bands in the grid.
Collapse All: Collapses all grouping bands in the grid.
ID/Code field
The unique identifier of the activity or WBS.
Name field
The name of the activity or WBS.
Getting Here
- Click Projects.
- On the Projects navigation bar, click Activities.
- Select the activities to which you want to assign relationships.
- Click Row Actions and select Assign Predecessors or Assign Successors.
Last Published Wednesday, July 10, 2024