Standard Work Week Tab of the Global Calendars Page
Overview
Use this tab to specify the length of work hours in a day or to calculate the total number of hours worked in a particular day.
Screen Elements
Work area
The typical work week that can be modified by day and hour. After choosing a calendar to be added while on the calendar tab, the Standard Work Week tab will display the similar template by days and hours.
Opens the Print Options dialog box.
Day label
The name of each day. This label begins the week with Sunday, ends with Saturday.
Total Hours field
The total number of work hours for each day.
Calendar View area
Enables you to view a day, week, month, or year of the calendar to identify standard time, nonwork time and calendar exceptions.
Work Period display
Displays a box that represents each work period in a day. If you change the number of hours covered by the work period boxes for a day, P6 updates the Total Hours field.
Tips:
- Modify the start day of the week in the Application Settings pane.
- There can be multiple work period boxes displayed in one day.
Getting Here
- Click Administration.
- On the Administration navigation bar, click Enterprise Data.
- On the Enterprise Data page, expand Global and click Global Calendars.
- On the Global Calendars page, click the Standard Work Week tab.
Related Topics
Setting Work Hours Per Time Period for Global Calendars
Configuring the Standard Work Week for Global Calendars
Modifying Calendar Days on Global Calendars
Setting the Default Global Calendar
Last Published Wednesday, July 10, 2024