Applying Actuals Based on the Auto Compute Actuals Method

The following processing occurs behind the scenes when you run the Apply Actuals command.

Example: A project's data date is June 1 and a user runs Apply Actuals with a new data date of June 20. An activity is planned for June 18 and is estimated to last 10 days until June 27. The activity's resource assignment has +5 days of lag (meaning it cannot start until June 23). When the user applies actuals on June 20, the activity's status is updated; however, because the assignment carries a resource lag beyond the new data date, it is not updated.