Assigning a Risk to an Activity

Assign a risk to an activity to explicitly identify the activity impacted by the risk.

You can assign a risk to an activity while you are adding project risks on the Risks page or while managing your activities on the Activities page.

To assign a risk to an activity from the Risks page:

  1. Click Projects.
  2. On the Projects navigation bar, click Risks.
  3. On the Risks page, click a risk.
  4. Click the Activities detail window and click Assign....
  5. In the Select Activity dialog box:
    1. Select one or more activities and click Select.
  6. On the Risks page, click Save.

To assign a risk to an activity from the Activities page:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
    1. On the Activities page, select the activity you want to assign a risk.
    2. On the Risks detail window, click Assign....
    3. In the Select Risk dialog box select a risk and click Assign.
    4. On the Activities page, click Save.

Related Topics

Managing Project Risks

Creating Project Risks

Risk Response Plans

Exporting Risk Data

Risks Page