Assigning Resource Curves to Resource or Role Assignments from the Resources Assignments Page

You can assign a resource distribution curve to any resource or role assignment on activities with a duration type of Fixed Duration and Units/Time or Fixed Duration & Units.

To assign a resource curve:

  1. Click Resources.
  2. On the Resources navigation bar, click Assignments.
  3. On the Assignments page:
    1. Display the Curves column if it is not visible on the table. To display the Curves column, click Customize View and click Columns, expand the General grouping and double-click Curve to move it to the Selected Columns list.
    2. On the Assignments page:
      • Click the row with the resource or role.
      • Double-click the Curve field, and clickSelect .
    3. In the Select Curves dialog box, choose a curve and click OK.
    4. On the Assignments page, click Save.

Tips:

Related Topics

Resource Assignments

About Resource Assignments

About Assignments Views

Working with Resource Assignments in the Gantt Chart

Viewing Assignment Unit and Cost Spreads

Assigning a Resource to an Activity Assignment

About Future Period Planning

Assigning Resource Curves to Resource or Role Assignments from the Activities Page