Configuring Advanced Scheduling Options

Configure advanced scheduling options to define float paths.

To configure advanced scheduling options:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page:
    1. Click Schedule....
    2. In the Schedule dialog box, click the Advanced tab.
    3. On the Advanced tab:
      • Select the Calculate Multiple Float Paths option.
      • Select Total Float or Free Float.
      • Enter or select a value for each field.
      • Click Save.