Assigning a Base Calendar to a Project Calendar

Assign a base calendar to determine holidays and exceptions for the selected project calendar.

To assign a base calendar:

  1. Click Administration.
  2. On the Administration navigation bar, click Enterprise Data.
  3. On the Enterprise Data page, expand Projects and click Project Calendars.
  4. On the Project Calendars page:
    1. Expand a project.

      Note: If the project you need is not open, click Open Project.... Choose one or more projects and click Open.

    2. Select a calendar to assign a base calendar.
    3. In the Base Calendar area, in the Search field click Select.
  5. In the Select Base Calendar dialog box, select a calendar and click Select.
  6. Click Save.

Related Topics

Configuring Project Calendars

Setting Work Hours Per Period for a Project Calendar

Configuring the Standard Work Week for Project Calendars

Modifying Calendar Days on Project Calendars

Changing a Project Calendar to a Global Calendar

Project Calendars Page



Last Published Wednesday, July 10, 2024