Viewing Role Usage

Use the Role view to view detailed role assignment information in histogram and spreadsheet format.

  1. Click Resources.
  2. On the Resources navigation bar, click Analysis.
  3. On the Analysis page, click the Role button.
  4. In the Role view:
    1. In the Group By list, choose to view roles by Role Hierarchy, Role Team, or by a role or assignment code.
    2. Click a role name.
    3. Click Customize View.
  5. In the Customize View dialog box:
    1. On the General tab:
      • In the Display list, choose the display format (units or costs).

        Choose units to view role use over the selected timescale interval; choose costs to view how much money is being spent over time.

      • In the Timescale list, choose a timescale interval.

        Choose a calendar interval (for example, Month/Week), or choose Financial Period to display the range of financial periods if financial periods are defined.

      • Select the Include assignments in restricted projects option to include a row in the view providing rolled-up data of the units and costs assigned in projects you are not permitted to access.
    2. On the Chart tab:
      • Choose to show or hide a Limit line.

        The Limit line shows maximum availability based on the resource's calendar and Max units/time setting, along with application settings for hours per time period.

      • Choose to show or hide the Allocation Limit line.

        This line shows the role's maximum availability based on Allocated planning values specified in the Resource Planning spreadsheet. Use this limit line to evaluate whether detailed activity assignments are in line with what was planned.

    3. Click Save.

Tips

Related Topics

Resource Analysis

About Resource Analysis

Analyzing Resource Allocations

Assigning Resources to Unstaffed Activities

Viewing Resource Usage

Exporting Resource or Role Usage Data

Analysis Page

Assigning Resources to Unstaffed Activities

Configuring General Settings



Last Published Wednesday, July 10, 2024