Configuring Microsoft Project Templates
Configure Microsoft Project templates to define data exchange options for both exporting to and importing from Microsoft Project.
To configure Microsoft Project templates:
- Click Projects.
- On the Projects navigation bar, click EPS.
- On the EPS page:
- Click the Actions
menu and select Import/Export Projects.
- In the Import/Export Projects dialog box, click the Import or Export tab.
- On the Import tab:
- In the Import Type list, select Microsoft Project XML.
- On the Import tab, click Browse in the File field and select a Microsoft Project XML file to import.
- Click Manage Templates.
- Or on the Export tab:
- In the Export Type list, select a Microsoft Project XML file type to export.
- Click Manage Templates.
- In the Manage Templates dialog box, click a template.
- In the Modify Template dialog box
- Configure the lists, options, and fields on each tab.
- Click Save.
- Click the Actions
Tips
The area you select from the Select Subject Area list on the Custom Field Mapping tab determines what appears in the Project Management and Microsoft Project Fields.
Note: Once data is exported from P6 into another project management tool, dates, durations and other data may no longer reflect those in P6 if the other project management tool recalculates this data.
Related Topics
About Importing and Exporting Projects
Configuring UN/CEFACT Templates
Importing Projects using Primavera XML Format
Exporting Projects using Primavera XML Format
Importing Projects using Primavera XER Format
Exporting Projects using Primavera XER
Importing Projects using Microsoft Project XML
Exporting Projects using Microsoft Project XML
Exporting Projects using UN/CEFACT XML
Exporting Projects using IPMDAR
Importing Projects from a Zip File
Exporting Projects to a Zip File
Last Published Wednesday, July 10, 2024