Level Resources Dialog Box (Reference)

If you select Activity Leveling priority, ascending levels higher priority activities first, and descending levels lower priority activities first.

If you select Project Leveling priority, ascending levels higher priority projects first, and descending levels lower priority projects first.

If you select Planned Start priority, ascending levels activities with earlier planned start dates first, and descending levels activities with later planned start dates first.

If you select Planned Finish priority, ascending levels activities with earlier planned finish dates first, and descending levels lower activities with later planned finish dates first.

If you select Planned Duration priority, ascending levels activities with shorter original or planned durations first, and descending levels activities with longer original or planned durations first.

If you select Remaining Duration priority, ascending levels activities with shorter remaining durations first, and descending levels activities with longer remaining duration first.

If you select Total Float priority, ascending levels activities with less total float or more critical activities first, and descending levels activities with more total float or less critical activities first.

If you select Early Start priority, ascending levels activities with earlier, early start dates first, and descending levels activities with later, early start dates first.

If you select Early Finish priority, ascending levels activities with earlier, early finish dates first, and descending levels activities with later, early finish dates first.

If you select Late Start priority, ascending levels activities with earlier, late start dates first, and descending levels activities with later, late start dates first.

If you select Late Finish priority, ascending levels activities with earlier, late finish dates first, and descending levels activities with later, late finish dates first.